About This Item
- Full text of this item is not available.
- Abstract PDFAbstract PDF(no subscription required)
Share This Item
The AAPG/Datapages Combined Publications Database
Houston Geological Society Bulletin
Abstract
Abstract: Mississippi Canyon 194
1989-91 "A" Platform Redevelopment
By
Mississippi Canyon 194 (Cognac) is located 12 miles
southeast of the mouth of the Mississipi River in 1024 feet
of water. The field extends over four 8 CS blocks acquired
by Shell, Amoco, and partners in the March, 1974 Federal
lease sale. Evaluation drilling started in 1975 and a 62-slot,
two-rig platform was installed in October, 1978. The initial
development
consisted of 61 wells drilled between 1978-82.
"Produce-while-drilling"
production
began in 1979 with permanent
facilities installed in 1982.
Production
peaked during 1984 at 83,000 BOPD and
130 MMCFPD. Prior to shut-in for redevelopment drilling in
1989,
production
declined to 11,000 BOPD and 45
MMCFPD. Cumulative
production
at that time was 120
MMBO and 220 MMCF. A 20-well redevelopment drilling
program was executed during 1989-91.
Production
after the
re-
development
peaked at 28,000 BOPD and 75 MMCFPD.
Preparation for the redevelopment began in 1987 with acquisition of a 3-D seismic survey. The interpreted survey indicated targets in new fault blocks as well as undrained areas in developed reservoirs. The seismic leads were supplemented by engineering and geological concepts on drainage and sand distribution in the field. The integration of geophysical, geological, and engineering data and concepts in planning and executing the redevelopment program is the subject of this presentation.
End_of_Record - Last_Page 12---------------