Abstract:

Reliable initial reservoir estimates can be made for a prospect without the benefit of reservoir engineering information. This is done by combining petrophysical Previous HitdataNext Hit such as sonic, gamma-ray, density, and resistivity logs with inverted Previous HitseismicNext Hit profiles and geologic models.

To delineate and appraise the reservoir volume adequately with Previous HitseismicNext Hit Previous HitdataNext Hit, the reduction, processing, and Previous HitdisplayNext Hit must be subject to strict quality control. The wavelet must be converted to zero phase, contracted and centered on the reflection coefficient that corresponds to the target beds. The useful spectrum of the Previous HitdataNext Hit must be as broad as possible to define the geologic boundaries properly. There must be a good estimate of the amplitude spectrum of the wavelet and a successful deconvolution to remove effects of the source signature. Noise maintenance or reduction must precede inversion of Previous HitseismicNext Hit Previous HitdataNext Hit to pseudo-sonic logs. The low-frequency gap in Previous HitseismicNext Hit records must be restored deterministically by the use of a geologic model with interval velocities specified. Time-variant pr cesses should be minimized or avoided. A reliable calibration of absolute transit times must be obtained given that the inversion algorithm was stable and satisfied all assumptions involved in its use. Finally, results

End_Page 261------------------------------

must be displayed or printed out so that Previous HitdataNext Hit manipulations can be reviewed critically.

Having achieved a rigid quality control, explorationists should now feel comfortable with initial reservoir estimates based on these Previous HitdataTop sets. Financial planning and forecasting can then proceed on a more secure basis earlier in the exploration and development of a prospect.

End_of_Article - Last_Page 262------------