Abstract


24th Annual Convention Proceedings (Volume 2), 1995
Pages 588-588

Results of Betung Reservoir Study: Abstract

Subarkah Kustowo1, Suherman Sudjai2, Sulfadi Nugroho3, Baktiar4

Abstract

Proven non-associated Previous HitgasNext Hit reserves in the Betung reservoir in the Baturaja Formation are 398.8 BSCF. The Betung structure was calculated initially to be capable of maintaining a Previous HitgasNext Hit supply of 40 to 60 MMSCFD for about 15 years. However, depletion of hydrocarbons amounting to 80% OGIP will largely depend on the distribution of reservoir parameters, reservoir pressure and depletion coordinates.

It is known that by producing Betung Previous HitgasNext Hit directly to the pipeline, the future reservoir pressure will not be sufficient to deliver the expected Previous HitgasNext Hit volume from the wells. Installation of Previous HitgasNext Hit compression will effectively lower the separator and wellhead pressures, which will improve the well flow rate and result in increased recovery of reserves.

In order to justify the installation of compression facilities, a specific depletion program will be required along with an assessment of the value of the Previous HitgasNext Hit recovered, using current production facility parameters. In order to realistically calculate the above factors, it is necessary to use a numerical simulator for predicting future Previous HitgasNext Hit deliverability.

The Betung reservoir simulation study was conducted in 1994, using the Eclipse-100/200 Network facility.

The following results were Previous HitobtainedNext Hit from this reservoir simulation study:

1. At a Previous HitgasNext Hit production rate of 40 MMSCFD from 1994 to the year 2006, total recovered Previous HitgasNext Hit is 342 BSCF or 64% OGIP. If Previous HitgasNext Hit compression is installed at year 2000, the recovered Previous HitgasNext Hit is 423 BSCF or 79% OGIP.

2. At a Previous HitgasNext Hit production rate of 60 MMSCFD from 1994 to the year 2001, total recovered Previous HitgasNext Hit is 342 BSCF or 64% OGIP. If Previous HitgasNext Hit compression is installed at year 1997, the recovered Previous HitgasTop is 417 BSCF or 78% OGIP.


 

Acknowledgments and Associated Footnotes

1 Pertamina

2 Pertamina

3 P.T. ESLI

4 Schlumberger-Geoquest